Potlatch Wastewater Reclamation Facilities Project
Begin Design |
May 2010 |
Conduct Survey and Field Engineering Studies |
May – August 2010 |
Prepare Construction Plans and Specifications |
May 2010 – May 2011 |
Complete Design |
May 2011 |
Complete Permitting |
August 2012 |
Advertise Project for Bid |
January 2012 |
Start Construction |
March 2012 |
Construction |
March 2012 - September 2013 |
Hoodsport Wastewater Reclamation Facilities Project - To Be Determined
Core Reservation Wastewater Facilities Project - To Be Determined